M V Ramana and Suvrat Raju | Hindustan Times
In his visit this week, the French President, Francois Hollande, is likely to urge the Indian Government to conclude a giant, but questionable, deal to purchase six nuclear European Pressurized Reactors (EPRs) from the French company Areva for Jaitapur (Maharashtra). Though marketed as “the most advanced” reactor, the EPR is commercially immature; not a single reactor has been commissioned anywhere in the world. Moreover, at the construction sites at Olkiluoto (Finland) and Flamanville (France), costs and construction times have escalated dramatically from the initial projected figures, suggesting that each reactor will cost about Rs. 60,000 crores.1<So, all six could cost in excess of 3.5 lakh crores.
To put this figure in perspective, each of the two reactors that Areva is hoping to sell in the next five years are larger than Maharashtra’s annual plan for 2012 (45,000 crores).2Shockingly, the Manmohan Singh Government agreed to purchase the reactors from Areva without even a nominal competitive bidding process. This contrasts sharply with the procurement rules in any branch of Government, including the Department of Atomic Energy (DAE), which mandate public tenders for any purchase above Rs. 10 lakh.
Cables revealed by Wikileaks suggest that this peremptory decision had been made by 2007.3 The Government’s rationale was laid out by the previous secretary of the DAE, Anil Kakodkar. In a surprisingly forthright article penned for a Marathi daily in 2011, Kakodkar wrote “we also have to keep in mind the commercial interests of foreign countries and of the companies there … America, Russia and France were the countries we made mediators in these efforts to lift sanctions, and hence, for the nurturing of their business interests, we made deals with them for nuclear projects.”4
Indian officials are aware that this considerate attitude is costly. In another cable revealed by Wikileaks, the General Manager of the Nuclear Power Corporation (NPCIL) admitted that India“ paid a ‘high’ price for French reactors from Areva.”5
Not surprisingly, the Government has been reticent about discussing the modalities of the contract it is negotiating with Areva. It has failed to support its strident assertions that “ the cost per unit of electricity from the Jaitapur plant … will be competitive to the other power plants”6with any substantive data on costs. When asked, it demurred, even in parliament, with the excuse that “the detailed project proposals … are under finalization.”7
To check the veracity of the Government’s claims, we recently used the best available public data on fuel prices and capital costs, assumed a substantial markdown to account for lower costs of labour in India, and estimated the expected tariff from the EPR reactors. This calculation involves some rather detailed accounting, but the basic procedure for setting the electricity tariff from nuclear plants was laid out the by the Executive Director of the NPCIL in 2008, during the debate on the Indo-US nuclear deal.<8
By adapting this procedure to the EPR—and using the most recent guidelines of the Central Electricity Regulatory Commission—we estimated that if NPCIL were to follow Government regulations faithfully, the first-year tariff from the EPR would be about Rs. 14 per unit!9This assumes that reactor construction starts next year and is completed on the same pattern as the Koodankulam I and II reactors, which, given the untested nature of the EPRs, is generous. The calculated tariff is a far cry from current or expected future tariffs from other baseload power projects
Since it cannot pass on such a high tariff onto consumers, the Government may simply absorb a large loss and sell electricity at a lower price. However, every rupee of under-recovery will cost the exchequer about Rs. 1,000 crores each year. Just to halve the tariff from the first two reactors down to Rs. 7, the Government may need to spend Rs. 14,000 crores per year.
This is in addition to indirect subsidies in the existing revenue model. For example, NPCIL plans to put in its equity early, and then let it lie idle with no returns, for the entire period of construction that may easily extend beyond a decade. The Government may increase these handouts in various ways—for example, by pressurizing public-sector banks to provide cheap credit for the project.